Ford’s Blue Oval City project has big task: Recruit workers to rural Tenn.

Ford Motor Co.’s Blue Oval City project, which aims to build electric vehicles and batteries in the small town of Stanton, Tenn., ranks as one of the biggest industrial undertakings in the automaker’s history. It also will be the largest investment in the state’s history, with a $5.6 billion price tag.

It’s an undertaking that will change the landscape of the area — for the community, for its work force and the people who live nearby, and for suppliers now plotting future plant investments, says one of the economic development leaders who helped Ford launch the project.

“This is not just going to be a local impact,” said Chris Berryman, who worked with Ford in his role as an auto industry recruiter for Tennessee Valley Authority Economic Development. “It won’t be only a seven-county impact. It’s going to be multistate. It will have an impact across West Tennessee and into the eastern section of Arkansas. It will reach into southern Kentucky and North Mississippi.

“It’s going to open up new possibilities for supplier locations, for companies that want to work with both Ford in Tennessee and Ford in Kentucky,” he said. “It will serve as a new anchor to supply OEM customers across this region.”

Stanton is at ground zero of the Blue Oval City megasite that covers 3,600 acres. But that community cannot begin to support the massive project by itself.

Stanton has a population of fewer than 500 people, and the entire county has barely 17,000. Building the Blue Oval City campus will require some 11,000 direct construction jobs and several thousand more related personnel. The completed factory will directly employ 5,700.

That work force will have to be recruited from some distance. The nearest population centers are Memphis, 50 miles southwest, and Jackson, Tenn., which has 68,000 people living 40 miles to the east. The region is largely agricultural, raising a housing question for the 5,700 plant workers and their families, as well as for construction workers in the meantime.

“Housing, to me, is going to be a critical issue for getting this campus built,” Berryman said. “Jackson will provide some of the housing needs, and Memphis will provide a lot of it. It will just depend on where people want to live, including the construction workers.”

TVA, a multistate utility and economic development agency, was a pioneer in offering pre-certified, obstacle-free megasites to recruit large auto plants, and the West Tennessee megasite was one of its first. Over the past two decades, TVA’s major recruitments have included Volkswagen in Chattanooga, Toyota in Tupelo, Miss., and Mazda-Toyota in Huntsville, Ala.

Blue Oval City will be more than a vehicle assembly plant. Ford intends for the project to showcase its fast-moving strategy to produce EVs. The site will house a large-scale battery manufacturing operation in partnership with Korean supplier SK Innovation. Equally significant, the campus will include a technology training center that will school thousands of workers in the art of EVs. Details of the training plan are not fully public, but the center is expected to provide skill certification for technologies that will apply across Ford’s emerging EV supply chain.

Berryman believes the influx of workers and construction personnel, participants in the technical training center, suppliers and other vendors will cause economic change across the region.